Texas authorized Evolve Energy’s proposed 42-turbine power facility in Guadalupe County on Nov. 16, after the governor directed a pause in data-center permitting.
The authorization concerns the power facility associated with a data-center project; it does not itself establish that the data center has every approval it needs.
From the source record
Governor Abbott Directs TCEQ To Halt Data Center PermitsOffice of the Texas Governor ↗
TCEQ’s technical review lists 1,605 megawatts of sitewide generating capacity for the Guadalupe County facility. That figure describes the reviewed facility’s capacity, not electricity already being generated. Residents can inspect the agency’s technical review for the scale of the proposal.
What the pause covered
On Sept. 21, Gov. Greg Abbott directed TCEQ to halt data-center permits pending a state audit. That directive is the starting point for understanding why a later state authorization for a facility associated with a data center matters in Guadalupe County.
TCEQ issued an Oct. 19 response addressing how it was applying the governor’s directive. The Nov. 16 authorization identifies the Evolve Energy power facility under registration 185103. Readers can use that registration number and the linked authorization to follow subsequent state records concerning the facility.