Guadalupe County proposes $55,844.85 more in engineering for Pioneer Road's low-water crossing north of Stagecoach Road. Commissioners are scheduled to consider the amendment Dec. 1; the posted materials establish a proposal, not an approved contract change.
The work would study about 1,000 feet of Pioneer Road north of Stagecoach Road for a future crossing design. For drivers who use that stretch, the proposed spending is for preliminary engineering, including a roadway and bridge schematic, rather than construction of a crossing.
From the source record
The proposed amendment raises the engineering contract cap by $55,844.85.Guadalupe County Dec. 1 Commissioners Court packet ↗
What the extra engineering covers
Kleinfelder's existing contract cap is $225,101.45. Amendment No. 2 would raise it to $280,946.30. The county would pay the increase without GLO or HUD reimbursement, according to the cover letter and amendment materials.
The proposed engineering scope calls for a preliminary corridor and right-of-way assessment, along with hydrology and hydraulics work. Its design criteria include a 25-year no-overtopping design and a 100-year no-rise comparison. Those are engineering study requirements in the proposal, not a finding that a finished crossing meets either standard.
The scope excludes capacity or operational enhancements at the Stagecoach Road–Pioneer Road intersection. That boundary matters to drivers: the proposed work addresses the crossing and nearby Pioneer Road segment, while intersection improvements are outside this amendment.