Schertz drivers and nearby property owners have until Dec. 2 to comment on TxDOT’s proposed FM 3009 realignment.
The roughly 1.7-mile plan would take the road from Borgfeld/Elbel Road toward FM 78 and carry it over FM 78 and the Union Pacific Railroad. TxDOT’s project page has the proposed schematic and an online comment form.
The proposal calls for approximately 29.5 acres of new right of way, subject to final design. For people along the corridor, that figure describes land TxDOT expects the project to need; it is not a final property boundary. The schematic on the project page is the useful record for checking where the proposed route would run.
Where and when
The places and times below come from the official pages linked with each one.
- Site
FM 3009 project corridor
FM 3009 from Borgfeld / Elbel Rd to FM 78, Schertz
Proposed realignment; design is not final
What the road plan includes
TxDOT identifies the project corridor as FM 3009 from Borgfeld/Elbel Road to FM 78. The proposed realignment includes an overpass of FM 78 and the Union Pacific Railroad, with ramps connecting the elevated route to the surrounding road network. That would change how drivers travel through the crossing area if the project proceeds as drawn.
The plan also includes sidewalks and shared-use paths. Those features matter to people walking or cycling near the corridor, while the proposed ramps and elevated crossing matter to drivers using FM 78 and FM 3009. TxDOT’s notice describes a proposal: design and construction are not final.