Schertz’s Weir Road records put $160,000 toward engineering while the damaged crossing’s projected completion date remains TBD.
The council adopted Ordinance 26-T-037, the first budget amendment for fiscal year 2026-27. The amendment draws on General Fund balance for engineering services on Weir Road repairs.
The interim repair is intended to reopen the Weir Road crossing at Cibolo Creek, which the city reported closed after rain damage. An Oct. 13 city update described severe damage to the crossing and said it was closed to traffic.
Map from the record

Where and when
The places and times below come from the official pages linked with each one.
- Site
Weir Road crossing
Weir Road at Cibolo Creek, Schertz
City project update reports the crossing closed after rain damage.
| Decision | Result | Count for–against | Voted no or abstained |
|---|---|---|---|
| Ordinance 26-T-037Adopt the first fiscal 2026–27 budget amendment, including Weir Road engineering fundsOfficial meeting recording, Adoption of Ordinance 26-T-037 ↗ | Passed | No count in the record | Not in the record |
Counts and names are shown only where the official record states them.
What does the $160,000 buy?
The engineering task order with Halff prices the work at $147,575, with a $160,000 ceiling. That ceiling and the later budget transfer describe the same design effort; they should not be added together as two separate engineering allocations.
The task order calls for design to reconstruct about 150 linear feet of roadway, culverts and headwalls at the creek. It also calls for a conceptual look at a longer-term improvement to the low-water crossing. The immediate design and the longer-term concept answer different questions: how to restore access first, and how the crossing might better withstand future high water.