Seguin staff sought a larger Nelda Street drainage design contract on Nov. 17 after engineers identified survey work beyond the original project boundary. The November staff memo put the proposed amendment before the City Council for the drainage project.
Map from the record

City of Seguin said in an email to Guadalupe.News: "The $50,000 amendment was approved and executed on 11/17/26." The city's response gives an outcome beyond the publicly indexed agenda item, which is marked “Agenda Ready.”
From the original design to a wider survey
A May 19 city memo recommended a $699,700 engineering agreement with Pape-Dawson for Nelda Street drainage design. A November staff memo says the council authorized that original agreement on May 19. The May staff memo described flood risk at more than 51 residential structures and at the Coliseum in the Nelda Street drainage area.
After engineers submitted a 30% design, Pape-Dawson asked for additional topographic survey and subsurface utility engineering beyond the original boundary. Its October request describes work around Short and Zunker streets, Walnut Branch and Austin Street, and Boenig Street.
City of Seguin said in an email to Guadalupe.News: "Therefore, to avoid disrupting the pipe going through private property, the western additional survey will contemplate an additional outfall that runs south on Boenig Street before heading west to the Guadalupe River." That is the city's description of a route under consideration for the survey, rather than a final construction alignment.