TSMC Arizona proposes a $22.62 billion advanced semiconductor campus in Brazos County.
Its filed application projects 2,099 direct jobs at the proposed College Station site; neither figure describes a completed investment. The proposed school property tax limit would apply in College Station ISD, outside Guadalupe County. The company is seeking a 10-year limit on the property's taxable value for school taxes.
Map from the record

That request is part of the proposed project, not an approved tax agreement or a final decision to build.
Reuters first reported the proposal Tuesday. Its report described the tax-limit request by the TSMC unit.
What happens next
The comptroller reviews the application before the governor and College Station ISD decide on the requested school tax limit. TSMC has not made a final investment decision. Readers can follow the proposed costs, jobs and site in the J0055 application as those decisions are recorded.