Schertz City Council approved a $39,052.50 change order for IH-35 NEX sewer relocation and raised Blackrock Construction's contract ceiling to $2.1 million. The work is part of moving city sewer lines out of the path of highway improvements.
Sewer reserves will initially fund the added work, with TxDOT reimbursement expected. The $2.1 million figure is the maximum amount authorized under the construction contract, not an amount the city has reported spending.
| Decision | Result | Count for–against | Voted no or abstained |
|---|---|---|---|
| Item 5Approved Change Order No. 4 for IH-35 NEX sewer relocation and raised Blackrock Construction's contract ceiling to $2.1 millionOfficial meeting recording, Item 5; 00:58:38–00:59:09 ↗ | Passed | 7 for, 0 against | None |
Counts and names are shown only where the official record states them.
From the source record
It adds change order No. 4 (about $39,000) and raises the not-to-exceed amount of BlackRock Construction's contract to $2.1 million for sewer relocation on the IH-35 NEXT project, which TxDOT will reimburse.Schertz City Council meeting recording ↗
The Nov. 17 action approved Resolution 26-R-127, including change order No. 4. The council's recorded vote was 7-0. The change order covers additional work needed to complete the sewer relocation.
The final construction cost and the timing of TxDOT's reimbursement remain the next figures to watch. Residents can inspect the council's recorded Item 5 action to verify the approval and contract limit.