Open site navigation
Explore Guadalupe.News
Send a tip

The Guadalupe Daily

Guadalupe County, before your second cup.

Guadalupe County news every morning, with links to the original sources.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.

The Guadalupe Daily

Guadalupe County, before your second cup.

Guadalupe County news every morning, with links to the original sources.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Send a tip

The Guadalupe Daily

Guadalupe County, before your second cup.

Guadalupe County news every morning, with links to the original sources.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Guadalupe County, TexasUpdated throughout the day
Local intelligence for a fast-growing county
Send a tip

The Guadalupe Daily

Guadalupe County, before your second cup.

Guadalupe County news every morning, with links to the original sources.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Guadalupe County news deskLocal reporting, every day

Schertz raises IH-35 sewer contract ceiling to $2.1 million

Schertz will initially use sewer service reserves to pay for $39,052.50 in added IH-35 NEX sewer relocation work, with TxDOT reimbursement expected.

Listen to this articleHear this story read aloudGuadalupe.News narrated edition
Ready · 0:00 / 1:44
Linocut illustration of a road above exposed earth, with a large pipe and a pipe opening beneath it.
Sewer pipes beneath a roadway represent the IH-35 sewer relocation; the image does not depict the reported work.Illustration: Guadalupe.News

Schertz City Council approved a $39,052.50 change order for IH-35 NEX sewer relocation and raised Blackrock Construction's contract ceiling to $2.1 million. The work is part of moving city sewer lines out of the path of highway improvements.

Sewer reserves will initially fund the added work, with TxDOT reimbursement expected. The $2.1 million figure is the maximum amount authorized under the construction contract, not an amount the city has reported spending.

How they votedSchertz City Council, Nov. 17, 2026
DecisionResultCount for–againstVoted no or abstained
Item 5Approved Change Order No. 4 for IH-35 NEX sewer relocation and raised Blackrock Construction's contract ceiling to $2.1 millionOfficial meeting recording, Item 5; 00:58:38–00:59:09 ↗Passed7 for, 0 againstNone

Counts and names are shown only where the official record states them.

From the source record

Recorded council actionResolution 26-R-127
It adds change order No. 4 (about $39,000) and raises the not-to-exceed amount of BlackRock Construction's contract to $2.1 million for sewer relocation on the IH-35 NEXT project, which TxDOT will reimburse.
Schertz City Council meeting recording ↗
Recorded action on Item 5, Nov. 17, 2026.

The Nov. 17 action approved Resolution 26-R-127, including change order No. 4. The council's recorded vote was 7-0. The change order covers additional work needed to complete the sewer relocation.

The final construction cost and the timing of TxDOT's reimbursement remain the next figures to watch. Residents can inspect the council's recorded Item 5 action to verify the approval and contract limit.

The Guadalupe Daily

Guadalupe County, before your second cup.

A clear morning briefing, with direct links to the records and sources behind each story.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.