Seguin council members are scheduled to consider $176,137.50 in added design work for a Geronimo Creek sewer alignment and water-main loop on Dec. 1.
The proposed water-main loop would connect a dead-end line to Monticello Street/Wakefield. The work is design, survey and related engineering; the proposal does not set a construction date or establish a change to anyone's water service.
Where and when
The places and times below come from the official pages linked with each one.
- Venue
Council Chambers
Council Chambers, Seguin
Dec. 1, 5:30 p.m.
Public and virtual meeting listed
Geronimo Creek and the water-main loop
Kimley-Horn's existing engineering agreement dates to April 16, 2024. Its proposed fourth amendment would add design for about 1,900 linear feet of 8-inch water main and about 1,900 linear feet of alternate 36-inch sewer alignment east of Geronimo Creek. The $176,137.50 addition includes environmental, geotechnical, survey and easement work as well as design.
For residents, the distinction is between planning a route and building it: the proposed amendment would pay for more engineering on the utility projects. Council's Dec. 1 action will establish whether that added scope enters the existing agreement.
Dam planning and utility vehicles
A separate proposal would authorize a $141,592 Freese and Nichols agreement for Walnut Branch wetlands analysis and a dam emergency action plan. The staff memo divides that into a $123,625 base fee and up to $17,967 in contingency, with Stormwater Utility Fee funds proposed as the payment source. The memo classifies the dam as high hazard because of its proximity to IH-10; that classification describes potential consequences, not a finding that failure is imminent.