Schertz’s IH-35 sewer relocation contract grew by $251,000.16 as buried utility conflicts forced changes to the work.
The council approved Resolution 26-R-127. The Nov. 17 action added a $39,052.50 fourth change order and raised BlackRock Construction’s not-to-exceed limit to $2.1 million. That limit is a ceiling, not a final construction bill.
Schertz plans to pay construction costs first from its sewer reserves. The arrangement puts city cash into the highway-related work before reimbursement, making the payment record the next useful measure of the city’s exposure.
Where and when
The places and times below come from the official pages linked with each one.
What changed in the contract
The original BlackRock Construction contract was $1,787,074, with an earlier not-to-exceed limit of $2 million. Those are different numbers: the contract is the price of the specified work, while the limit caps what the city may authorize under the agreement.
The first two change orders added $8,646.34 apiece for subsurface utility engineering locations. A third added $194,654.98 for a revised alignment at bore 2. Before the fourth order, the contract stood at $1,999,021.66.