Open site navigation
Explore Guadalupe.News
Send a tip

The Guadalupe Daily

Guadalupe County, before your second cup.

Guadalupe County news every morning, with links to the original sources.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.

The Guadalupe Daily

Guadalupe County, before your second cup.

Guadalupe County news every morning, with links to the original sources.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Send a tip

The Guadalupe Daily

Guadalupe County, before your second cup.

Guadalupe County news every morning, with links to the original sources.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Guadalupe County, TexasUpdated throughout the day
Local intelligence for a fast-growing county
Send a tip

The Guadalupe Daily

Guadalupe County, before your second cup.

Guadalupe County news every morning, with links to the original sources.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Guadalupe County news deskLocal reporting, every day

Schertz’s IH-35 sewer contract grows $251,000 after utility conflicts

Schertz approved a $2.1 million contract ceiling after underground utility conflicts added $251,000.16 to IH-35 sewer relocation work. Sewer reserves cover construction first; TxDOT is expected to reimburse the city.

Listen to this articleHear this story read aloudGuadalupe.News narrated edition
Ready · 0:00 / 5:47
Linocut-style highway scene with cars and trucks above a cutaway of buried white pipes and a curved green utility line.
Highway traffic above buried pipes and a green utility line, representing sewer relocation work.Illustration: Guadalupe.News

Schertz’s IH-35 sewer relocation contract grew by $251,000.16 as buried utility conflicts forced changes to the work.

The council approved Resolution 26-R-127. The Nov. 17 action added a $39,052.50 fourth change order and raised BlackRock Construction’s not-to-exceed limit to $2.1 million. That limit is a ceiling, not a final construction bill.

Utility conflicts added $251,000.16 to the IH-35 sewer contractContract value at three stages, dollars
Source: Schertz City Council, Nov. 17, 2026, item 5 staff memo.The $251,000.16 increase is $2,038,074.16 minus the $1,787,074 original contract.

Schertz plans to pay construction costs first from its sewer reserves. The arrangement puts city cash into the highway-related work before reimbursement, making the payment record the next useful measure of the city’s exposure.

Map

Where and when

The places and times below come from the official pages linked with each one.

What changed in the contract

The original BlackRock Construction contract was $1,787,074, with an earlier not-to-exceed limit of $2 million. Those are different numbers: the contract is the price of the specified work, while the limit caps what the city may authorize under the agreement.

The first two change orders added $8,646.34 apiece for subsurface utility engineering locations. A third added $194,654.98 for a revised alignment at bore 2. Before the fourth order, the contract stood at $1,999,021.66.

The fourth order adds $39,052.50 for further revised bore work, bringing the contract to $2,038,074.16. The approved $2.1 million ceiling leaves $61,925.84 above that revised amount. That difference is room under the authorization, not another change order or a payment already made.

Schertz IH-35 sewer relocation contract amounts, through the Nov. 17, 2026 action
Contract stage or amendmentAmount
Original construction contract$1,787,074.00
Change order 1: utility location 1$8,646.34
Change order 2: utility location 2$8,646.34
Change order 3: bore 2 alignment$194,654.98
Contract before change order 4$1,999,021.66
Change order 4: revised bore work$39,052.50
Revised contract after change order 4$2,038,074.16
Approved not-to-exceed limit$2,100,000.00

Change orders are additions; the contract-stage rows are running totals. The not-to-exceed limit is an authorization ceiling. Source: Nov. 17 item 5 staff memo and verified council outcome.

Why the bore work changed

Schertz staff attributed the added work to fiber, gas, telephone and power lines whose depths differed from the subsurface utility information supplied for the TxDOT project, or whose relocations had not yet occurred. Staff and TxDOT approved a revised crossing design to avoid those conflicts. The memo ties the cost increase to that physical problem, rather than to an expanded sewer project.

Who carries the bill first

The item memo says TxDOT will reimburse Schertz for construction costs. Until that happens, the city’s sewer reserves are the stated source of construction money. The $2.1 million authorization sets the most the contract may reach under this approval; it does not establish what the contractor will ultimately bill or what TxDOT will ultimately pay.

For residents following the project’s cost, the next useful documents are a city reimbursement record and the project closeout. They can show the amount paid back and the time between Schertz’s construction payments and TxDOT’s reimbursement. The city’s item 5 cost memo shows the contract changes approved so far.

The Guadalupe Daily

Guadalupe County, before your second cup.

A clear morning briefing, with direct links to the records and sources behind each story.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.