A signed agreement with Halff Associates sets a $139,202 ceiling for engineering services on Seguin's Olive Street drainage improvements. The work concerns streets in the city's Risk Area C, but the agreement is for engineering rather than construction.
The agreement's roadway scope covers 375 linear feet of N. Olive Street and 875 linear feet of E. Mountain Street. Those lengths identify the roadway work described for design; they do not establish that crews have been hired or construction has begun.
What the fee covers
The contract lists a $131,702 base fee within its total ceiling, with additional services accounting for the remainder. For nearby residents, that ceiling limits Halff's engineering services; it is not a price for building the drainage improvements.
A Risk Area C planning map dated Nov. 3, 2025, depicts Olive Street between E. Mountain and E. Walnut streets. It sketches alleyway work, a channel on N. Olive connected to an existing drain near E. Mountain, curb and gutter, inlets, detention, and possible access or road changes. The map is older planning material; its options should not be read as the final design authorized by this agreement.
Map from the record

The Nov. 17 agenda scheduled City Council consideration of the Halff engineering agreement. The council's adopted resolution or minutes are the next records to consult for its action; the agreement itself does not establish a separate construction authorization.