Seguin’s proposed 10th North Heideke drainage change order would bring the contract to $17,813,903.74 and 653 days, $97,905.05 below its original price but 43 days longer.
The proposed work addresses a sewer conflict on Martindale, an inlet at Seidemann, a curb at Hays and retaining-wall work at Starcke. Seguin City Council is scheduled to consider the order Dec. 1, according to the proposed change-order form.
What the contract math shows
The original contract was $17,911,808.79 for 610 days. Immediately before proposed Order 10, the form lists a contract price of $17,748,612.86 and 610 days.
The requested order adds $65,290.88 to that prior price. The result would still be $97,905.05, or about 0.55%, below the original contract amount. These are contract amounts, not a tally of payments made.
| Contract stage | Price |
|---|---|
| Original contract | $17,911,808.79 |
| Before proposed Order 10 | $17,748,612.86 |
| With proposed Order 10 | $17,813,903.74 |
The final row is proposed, not an approved contract price.