Seguin’s Nelda drainage survey tests another path to the river

Seguin approved a $50,000 survey that tests another river outfall for a drainage project targeting repeated flooding near Nelda Street. Residents’ next answer is the selected route.

Listen to this articleHear this story read aloudGuadalupe.News narrated edition
Ready · 0:00 / 4:45
Ink illustration of a dashed route marked by posts crossing grassy ground toward a green river, with a building and outdoor tables at left.
A dashed route crosses open ground toward a river, suggesting a drainage outfall under study.Illustration: Guadalupe.News

Seguin’s extra $50,000 for Nelda Street drainage design pays to study a possible Boenig Street outfall meant to avoid disturbing a pipe crossing private property. Why does that possibility require another survey?

Map from the record

Aerial map of the Nelda Street drainage project area in Seguin. A red outline marks the original project boundary, and blue shaded areas extending north, south and east mark the additional survey boundary.
Where the added Nelda Street survey reaches. The city's map, labeled "Subsurface Utility Engineering Scope," outlines the original project boundary in red. The additional survey areas the $50,000 amendment pays for are shaded in blue.Map: City of Seguin · View the original map (PDF) ↗

The original engineering contract, authorized in May, totaled $699,700 including contingency. The city says it approved and executed the amendment Nov. 17, bringing the design contract to $749,700. This is money for design work, rather than a completed drain.

The city says the project targets repeated stormwater impacts to more than 51 residential structures and flooding at the Coliseum emergency shelter. Its November memo describes three outfall points. For people in that drainage area, where the water ultimately goes is more useful than the amendment’s headline price.

Map

Where and when

The places and times below come from the official pages linked with each one.

  • Site

    Nelda Street drainage project

    Nelda Street, Seguin

    Drainage project described in the city’s amendment memo.

    Source: City of Seguin ↗

  • Route

    Possible western outfall route

    Boenig Street, Seguin

    The city says the additional survey will contemplate this route toward the Guadalupe River.

    Source: City of Seguin ↗

What the added money buys

The engineering request divides the amendment among topographic survey, underground utility investigation and project management. The survey is the largest piece. It expands measurements beyond the original contract boundary after design changes coordinated following the 30% submittal.

How the $50,000 Nelda Street design amendment is allocated in the Oct. 22 engineering request
WorkAmount
Topographic survey$34,950
Subsurface utility work$10,040
Project management$5,010

These are design and investigation costs, not a construction estimate.

That breakdown answers a narrower question than the approval alone: Seguin is paying to learn where an alternative can fit and what utilities are in its way. The Rios Group’s utility-work scope covers roughly 1,500 linear feet south on Boenig Street, 525 feet north on Short Street and 550 feet east along SH 123 toward Walnut Creek. It expressly excludes private property and proposed right of way.

Why the path matters

The city’s response says the additional western survey will contemplate an outfall running south on Boenig Street, then west to the Guadalupe River. The word “contemplate” matters: this is a route being examined, not a construction alignment being announced. Avoiding disruption to the existing pipe is the stated reason to examine it.

Our earlier report covered the city’s approval of the design amendment. The new question is whether the added measurements make the Boenig option workable—and how that choice would shape the eventual project for nearby residents.

Who pays for this step?

The November city memo identifies stormwater utility fee bonds as funding for the professional-services amendment. The May memo identified certificates of obligation for the original design. Those descriptions concern different steps; the project-account ledger and bond records are the next way to check how the design bills were actually financed.

The next number to watch

The utility-work scope estimates mobilization within three weeks of notice to proceed and 27 working days for that investigation after its prerequisites. Those are survey milestones. The next design submittal or final outfall selection—not the survey timetable—will show which route Seguin intends to carry toward construction. Readers can inspect the engineering request to see exactly what was added.

The Guadalupe Daily

Guadalupe County, before your second cup.

A clear morning briefing, with direct links to the records and sources behind each story.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.