Seguin’s extra $50,000 for Nelda Street drainage design pays to study a possible Boenig Street outfall meant to avoid disturbing a pipe crossing private property. Why does that possibility require another survey?
Map from the record

The original engineering contract, authorized in May, totaled $699,700 including contingency. The city says it approved and executed the amendment Nov. 17, bringing the design contract to $749,700. This is money for design work, rather than a completed drain.
The city says the project targets repeated stormwater impacts to more than 51 residential structures and flooding at the Coliseum emergency shelter. Its November memo describes three outfall points. For people in that drainage area, where the water ultimately goes is more useful than the amendment’s headline price.
Where and when
The places and times below come from the official pages linked with each one.
- Site
Nelda Street drainage project
Nelda Street, Seguin
Drainage project described in the city’s amendment memo.
- Route
Possible western outfall route
Boenig Street, Seguin
The city says the additional survey will contemplate this route toward the Guadalupe River.
What the added money buys
The engineering request divides the amendment among topographic survey, underground utility investigation and project management. The survey is the largest piece. It expands measurements beyond the original contract boundary after design changes coordinated following the 30% submittal.
| Work | Amount |
|---|---|
| Topographic survey | $34,950 |
| Subsurface utility work | $10,040 |
| Project management | $5,010 |
These are design and investigation costs, not a construction estimate.