Seguin council is scheduled to consider adding $50,000 to the Nelda Street Drainage Improvements design contract on Nov. 17. The proposed addition would pay for more survey and underground utility work before the drainage design advances.
If approved, total design authorization would rise to $749,700. The memo identifies stormwater utility fee bonds as the funding source for the proposed amendment. Council's Nov. 17 agenda lists the amendment as consent item 26-497; the posted resolution is unsigned.
Where and when
The places and times below come from the official pages linked with each one.
- Site
Nelda Street drainage project
Nelda Street, Seguin
Proposed design amendment; no street closure established
What the additional work covers
The existing professional services authorization consists of a $673,151 base fee and a $26,549 contingency under Resolution 2026R-096. The proposed $50,000 addition is separate from those earlier amounts.
The added design work includes surveying outside the original project boundary and subsurface utility engineering for three outfall points. The amendment request describes survey areas near Short and Zunker streets, the Walnut Branch bridge at Austin Street, and Boenig Street from Nelda Street toward the golf course. It lists $34,950 for topographic survey, $10,040 for subsurface utility engineering and $5,010 for project management.
Why the design matters
City staff says the drainage project targets homes on Nelda and Elsik streets and emergency operations at the Coliseum. Staff says the proposed work would protect more than 51 residential structures; that figure describes the project's intended reach, not a measured result of the $50,000 design amendment.
The next verification point is council's Nov. 17 disposition of item 26-497. Residents can inspect the proposed amounts and work areas in the amendment request while the council's outcome record establishes whether the addition was authorized.