Open site navigation
Explore Guadalupe.News
Send a tip

The Guadalupe Daily

Guadalupe County, before your second cup.

Guadalupe County news every morning, with links to the original sources.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.

The Guadalupe Daily

Guadalupe County, before your second cup.

Guadalupe County news every morning, with links to the original sources.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Send a tip

The Guadalupe Daily

Guadalupe County, before your second cup.

Guadalupe County news every morning, with links to the original sources.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Guadalupe County, TexasUpdated throughout the day
Local intelligence for a fast-growing county
Send a tip

The Guadalupe Daily

Guadalupe County, before your second cup.

Guadalupe County news every morning, with links to the original sources.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Guadalupe County news deskLocal reporting, every day

What would Seguin take on under the proposed Town Center water deal?

Seguin would pay for an offsite water line and maintain accepted internal facilities under a proposed Town Center agreement. Future customers’ rates would follow city classes; council takes up the deal Nov. 3.

Listen to this articleGuadalupe.News narrated edition
Ready · 0:00 / 5:45
Illustrated water pipes lie beside a pale road and grassy field, with utility poles and low hills in the distance.
Illustration: Water pipes beside an open field represent the proposed Town Center water system; this does not depict the reported project site.Original editorial illustration; not a photograph and does not depict the reported event or an exact property.Guadalupe.News Visual Desk · Original illustration · Source ↗ · Guadalupe.News original illustration ↗

Seguin's proposed Town Center water deal puts the offsite line on the city and internal water pipes on Guadalupe County MUD No. 3. So how much of the system would Seguin inherit?

The proposal is before the City Council as item 26-491 on Nov. 3. Staff describes a development of more than 539 acres with projected ultimate water demand of 862,272 gallons a day, or about 2,028 living-unit equivalents. Those are planning figures, not an approved construction bill or a household charge.

Site plan from the record

Plan drawing of a proposed 16-inch waterline bored beneath IH-10 in a steel casing, tying into existing 8-inch and 16-inch waterlines, with easements and TxDOT right-of-way labeled.
Where the offsite water line crosses IH-10. Exhibit labeled "Newquest Water Line IH-10 Bore" shows a proposed 16-inch PVC waterline in a 36-inch steel casing bored under IH-10, about 476 feet long, connecting to existing 8-inch and 16-inch PVC waterlines.Site plan: TRC Engineers, Inc. / City of Seguin · View the original document (PDF) ↗

Which pipes would each side take on?

Here is how the draft divides the work. Section 2.01 puts phased internal water construction on the district. Section 2.02 puts design and construction of the offsite line, along with needed rights-of-way, on Seguin at its sole cost. Sections 3.01 and 3.02 then have the district convey accepted internal facilities to the city, which would operate and maintain them at its own expense.

Proposed construction and service duties in the Town Center agreement, as of Oct. 30, 2026
Part of systemBuilds or paysAfter construction
Internal water facilitiesDistrict builds in phases (§2.01)Accepted works go to Seguin for operation and maintenance (§§3.01–3.02)
Offsite water lineSeguin designs and builds at its sole cost (§2.02)City water system responsibility under the draft
Later supply expansionSeguin funds needs beyond the district's impact-fee contribution (§2.02)Additional city supply capacity
Retail service and metersSeguin installs meters (§3.03)Seguin serves customers and receives retail revenue (§3.03)

These are proposed duties, not completed construction or an adopted cost estimate.

Future Town Center water customers would pay Seguin's uniform retail rates for comparable customer classes if the agreement takes effect. The city would receive retail revenue and comparable connection charges. The city would also pay for the offsite line, later supply needs and maintenance.

The district could issue its own bonds under Sections 4.01 and 4.02. Those would remain district obligations unless the city dissolved the district and assumed its liabilities. Keeping that distinction matters: a district bond is not, by itself, a Seguin utility bill or city debt.

What could change the cost?

The city also would fund later supply expansion, while the district's contribution is capped at impact fees under Section 2.02. Under Section 2.05, Seguin would pay agreed incremental costs if it asks for oversized facilities. These provisions set responsibilities; estimating a household effect would require construction prices, a funding plan, applicable fees and the number of paying customers.

There is a demand-measure puzzle, too. The staff memo uses 360 gallons a day per living-unit equivalent, while Article I of the draft defines one equivalent as 425 gallons a day. Section 2.02 also gives the project total as 862,272 gallons a day for about 2,028 equivalents. Council will need a consistent basis to judge how much capacity the deal requires.

The staff memo estimates Jan. 31, 2027, for the offsite line. The agreement instead sets substantial completion within six weeks after permits are obtained. If the city misses that contractual timing, the district may build the line and receive impact-fee credits. The IH-10 exhibit shows a proposed 16-inch line and bore, not a finished route.

What happens next?

The project lies inside Springs Hill's water certificate area, so Seguin service depends on a transfer, single certification or release. The proposal does not itself establish that the service-area change has occurred. The Nov. 3 council decision, an executed agreement and the relevant certification and permit filings are the next records to check before assigning costs to future customers.

Related coverage

The Guadalupe Daily

Guadalupe County, before your second cup.

A clear morning briefing, with direct links to the records and sources behind each story.

By subscribing, you agree to receive The Guadalupe Daily and to our Terms and Privacy Policy. Unsubscribe anytime.